Well done!

Construction Worker holding level and giving thumbs up

You chose the correct answer. If our calculations were correct, we have 14 weeks between today and the day the steel is needed on-site, but the processing time based on all our current information is calculating out to be about 15 weeks. This would put our steel on-site a week late!! Not good.

So...

Although our answer was correct, we still have a problem….

​

Our steel will not be on-site before we need it. Let’s continue the exercise to come up with different solutions to fix this problem. Explore some of the options below to see how we can maintain our schedule.

Chalkboard lightbulb with brainstorm bubbles

Choose a solution!

Pick from the options below: